Vad är orsaken till att bygglogistiken inte prioriteras i projekteringsskedet?: What is the reason why construction logistics is not prioritized in the design phase?
2025 (Swedish)Independent thesis Basic level (degree of Bachelor), 10 credits / 15 HE credits
Student thesisAlternative title
What is the reason why construction logistics is not prioritized in the design phase? : A study on the relationship of construction logistics to Lean Construction and sustainable development (English)
Abstract [sv]
Byggbranschen befinner sig i en expansiv fas med ökande krav på bostadsproduktion och utveckling av samhällsinfrastruktur, särskilt i tättbebyggda områden där begränsade ytor och komplexa projekt ställer höga krav på effektiv bygglogistik. Trots dess avgörande roll prioriteras logistiken ofta inte i projekteringsfasen, vilket resulterar i ineffektiva leveranser, ökade kostnader, förseningar samt negativa miljö- och arbetsmiljöpåverkan.
Detta examensarbete, i samarbete med Svensk Bygglogistik, undersöker varför bygglogistiken ofta hanteras först under produktionsfasen, vilka konsekvenser detta har för projektens hållbarhet och effektivitet, samt hur Lean Construction kan användas för att förbättra logistikplaneringen. Studien bygger på en kombination av intervjuer, studiebesök, litteraturstudie samt en enkät.
Resultaten pekar på att logistik ofta nedprioriteras tidigt på grund av bristande kunskap, traditionella arbetsmetoder och en uppfattning att logistiken innebär extra kostnader. Projektets storlek, geografiska läge och närvaron av pågående verksamheter påverkar också logistiska beslut. Den sena logistikhanteringen leder till ökade utsläpp, kostnader och en osäker arbetsmiljö med högre risk för olyckor och stress.
Studien identifierar ett tydligt men ofta förbisett samband mellan god bygglogistik och hållbar utveckling. Effektiv logistik minskar miljöpåverkan, förbättrar arbetsmiljön och bidrar till kostnadseffektivitet, även om dessa fördelar ofta är svåra att kvantifiera. Lean Construction framstår som ett kraftfullt verktyg för att eliminera slöseri och skapa strukturerade arbetsprocesser, men kräver anpassning till byggsektorns unika, projektbaserade natur för att få genomslag.
För att realisera bygglogistikens fulla potential krävs tidig involvering av logistikkompetens, tydlig ansvarsfördelning och en ökad beställarkompetens för att säkerställa att logistiska krav ställs redan i projekteringsfasen. En sådan proaktiv och integrerad planering är avgörande för att förbättra effektivitet, hållbarhet och arbetsmiljö i framtidens byggprojekt.
Abstract [en]
The construction industry is currently in an expansion phase, with increasing demands for housing and development of community infrastructure, especially in densely built-up areas where limited space and complex projects place high demands on efficient construction logistics. Despite its crucial role, logistics is often not prioritized during the design phase, resulting in inefficient deliveries, increased costs, delays, as well environmental and occupational health impacts.
This thesis, conducted in collaboration with Svensk Bygglogistik, investigates why construction logistics is often addressed only during the production phase, the consequences this has for project sustainability and efficiency, and how Lean Construction can be utilized to improve logistics planning. The study is based on a combination of interviews, site visits, literature review, and a survey.
The results indicate that logistics is often deprioritized early on due to a lack of knowledge, traditional working methods, and a perception that logistics entails additional costs. The project’s size, geographical location, and the presence of ongoing operations also influence logistical decisions. Late logistics management leads to increased emissions, costs, and an unsafe work environment with a higher risk of accidents and stress.
The study identifies a clear but often overlooked connection between good construction logistics and sustainable development. Efficient logistics reduces environmental impact, improves the work environment, and contributes to cost-effectiveness, although these benefits are often difficult to quantify. Lean Construction emerges as a powerful tool to eliminate waste and create structured work processes but requires adaptation to the construction sector’s unique, project-based nature to be effective.
To realize the full potential of construction logistics, early involvement of logistics expertise, clear responsibility allocation, and increased client competence are required to ensure that logistical requirements are established during the design phase. Such proactive and integrated planning is crucial for improving efficiency, sustainability, and occupational health in future construction projects.
Place, publisher, year, edition, pages
2025.
Series
TRITA-ABE-MBT ; 25606
Keywords [en]
Lean Construction, Lean, sustainable development, construction logistics, total cost, planning and design, construction phase, just-in-time, jidoka, occupational health and safety, climate targets.
Keywords [sv]
Lean Construction, Lean, hållbar utveckling, bygglogistik, totalkostnad, projektering, produktion, just-in-time, jidoka, klimatmål, arbetsmiljö, miljömål.
National Category
Engineering and Technology
Identifiers
URN: urn:nbn:se:kth:diva-368902OAI: oai:DiVA.org:kth-368902DiVA, id: diva2:1991224
External cooperation
Svensk Bygglogistik
Supervisors
Examiners
2025-08-222025-08-22