Förbättringsarbete för beställning och hantering av grafitmaterial: Vid CVD-beläggningen, Sandvik Coromant Gimo
Uppsala University, Disciplinary Domain of Science and Technology, Technology, Department of Engineering Sciences, Industrial Engineering & Management.
2016 (Swedish)Independent thesis Basic level (professional degree), 10 credits / 15 HE creditsStudent thesisAlternative title
Improvements in ordering and handling of graphite material (English)
Abstract [en]

Sandvik Coromant is a worldwide supplier of tools, tooling solutions and know-how

to the metalworking industry. Sandvik Coromant in Gimo is manufacturing various

models of carbide inserts for metal cutting. The majority of the inserts are coated to

create a unique combination of toughness and wear resistance, even in complex



The inserts are transported through the coating process in a charge, the charge

almost completely consists of graphite materials of various design e.g. load carriers.

The graphite material will eventually wear out and must be replaced with new

graphite. Sandvik puts through several charges per day which makes the consumption

of graphite great. The graphite material is relatively expensive and Sandvik therefore

spends large amounts of money each year on new graphite.


Unclear structure in the operation of the order and management of new graphite

materials have led to e.g. unnecessary inventories, at times material shortages and

uneven loading of the coating ovens. The aim of the thesis has been to investigate and

analyze current way of working regarding ordering and handling of graphite materials

and to come up with a concrete proposal for improvement of the working methods.


The project was divided into two phases, a situation analysis and a design phase.

Phase one was to make an overall situation analysis to create a clear picture of how

the work is done today (May 2016) and find out areas for improvement. Current

situation analysis was based on interviews and practice with operators, technicians

and the production manager for the concerned department.

Phase two was the design of an improvement proposal for a new way to work. It was

initiated by a literature study to find ideas, possible concepts and a firmer relevant

foundation of knowledge. In order to define the project, a decision about the projects

boundaries was made with the department manager, production manager and the

supervisor. The design was then created through a workshop / meeting with

operators in the department. The workshop was coordinated to go through the

problem and get perspectives and views on how a new way of working could be



The result was a proposal for a new way of working for ordering graphite material. It

is based on having a system that uses kanban card to visualizes when the order are to

be made and initiates the order process. The proposed approach organizes the

inventory better, thereby reducing inventory levels for new pin carriers by 40%. It

also means a possible reduction of the inventory of graphite storage at the supplier,

the storage at the supplier could be reduced by 43%.

Place, publisher, year, edition, pages
2016. , 55 p.
Keyword [sv]
Grafitmaterial, arbetssätt, processanalys, förbättringsförslag, lagerstyrning
National Category
Production Engineering, Human Work Science and Ergonomics
URN: urn:nbn:se:uu:diva-296471ISRN: UTH-INGUTB-EX-M-2016/19-SEOAI: diva2:938499
Educational program
Bachelor Programme in Mechanical Engineering
Available from: 2016-06-17 Created: 2016-06-16 Last updated: 2016-06-17Bibliographically approved

Open Access in DiVA

fulltext(1166 kB)42 downloads
File information
File name FULLTEXT01.pdfFile size 1166 kBChecksum SHA-512
Type fulltextMimetype application/pdf

By organisation
Industrial Engineering & Management
Production Engineering, Human Work Science and Ergonomics

Search outside of DiVA

GoogleGoogle Scholar
Total: 42 downloads
The number of downloads is the sum of all downloads of full texts. It may include eg previous versions that are now no longer available

Total: 111 hits
ReferencesLink to record
Permanent link

Direct link