Value of stochasticity in hydropower planning optimization
KTH, School of Electrical Engineering (EES), Electric Power Systems.
2012 (English)Independent thesis Advanced level (degree of Master (Two Years)), 20 credits / 30 HE creditsStudent thesis
Abstract [en]

With respect to market liberalization, efficient use of resources is becoming more important for players in the market. In order to achieve that different optimization techniques were developed which enable better operational efficiency. These techniques can be segmented in to two different categories, depending on their time horizon:

• Yearly time horizon – mid-term hydropower scheduling

• Daily time horizon – short-term hydropower scheduling

These two time horizons account for two case studies presented in this thesis.

In the first case study (mid-term planning), the focus is on determining power plant’s optimal operating strategy, while taking into account the uncertainty in inflows and prices. Stochastic dynamic programming has been chosen as mid-term optimization technique. Since stochastic dynamic programming calls for a discretization of control and state variables, it may fall under the curse of dimensionality and therefore, the modeling of stochastic variables is important. By implementing a randomized search heuristic, a genetic algorithm, into the existing stochastic dynamic programming schema, the optimal way of using the stochasticity tries tobe found. Two price models are compared based on the economic quality of the result. The results give support to the idea of using search heuristics to determine the optimal stochasticity setup, however, some deviations from the expected results occur. Second case study deals with short-term hydropower planning, with a focus on satisfying the predefined demand schedule while obtaining maximum profit. With short-term hydropower planning being a nonlinear and nonconvex problem, the main focus is on the linearization ofunit performance curves, as well as satisfying technical constraints from the power plan tperspective. This optimization techniques also includes the water value in the solution. The problem has been solved by means of mixed integer linear programming. The results from the second case study are fully in line with the expectations and it is shown that mixed integer linear programming approach gives good results with good computational time. Suggested improvements to the model and potential for future work can be found in the final chapter of this thesis.

Place, publisher, year, edition, pages
2012. , 82 p.
EES Examensarbete / Master Thesis, XR-EE-ES 2012:008
National Category
Electrical Engineering, Electronic Engineering, Information Engineering
URN: urn:nbn:se:kth:diva-103184OAI: diva2:558829
Educational program
Master of Science - Electric Power Engineering
Available from: 2012-10-10 Created: 2012-10-05 Last updated: 2012-10-10Bibliographically approved

Open Access in DiVA

FULLTEXT(1580 kB)54 downloads
File information
File name FULLTEXT01.pdfFile size 1580 kBChecksum SHA-512
Type fulltextMimetype application/pdf

By organisation
Electric Power Systems
Electrical Engineering, Electronic Engineering, Information Engineering

Search outside of DiVA

GoogleGoogle Scholar
Total: 54 downloads
The number of downloads is the sum of all downloads of full texts. It may include eg previous versions that are now no longer available

Total: 79 hits
ReferencesLink to record
Permanent link

Direct link