Tids- och kostnadseffektivisera byggproduktionen: Slöserier och störningar
KTH, School of Architecture and the Built Environment (ABE), Civil and Architectural Engineering, Building Technology and Design.
KTH, School of Architecture and the Built Environment (ABE), Civil and Architectural Engineering, Building Technology and Design.
2018 (Swedish)Independent thesis Basic level (university diploma), 10 credits / 15 HE creditsStudent thesisAlternative title
Making construction management more efficient through time and money : Waste and interferences (English)
Abstract [sv]

Största utmaningen byggindustrierna har i dagens läge är att reducera onödiga kostnader och onödigt arbete samt att effektivisera arbetet i form av tid och pengar. Detta är en fråga och en undersökning som gjorts ett flertal gånger under de senaste åren eftersom att det är ett stort problem inom de flesta byggbranscher. Denna rapport är skriven i uppdrag av Peab i syfte att identifiera slöserierna och kritiska störningar, för att sedan ta fram åtgärdsförslag för att reducera slöseriet av tiden och kostnaderna för framtida projekt

Fyra olika, slutförda anläggningsprojekt har undersökts i uppdrag av Peab belägna i Stockholm. Dessa projekt omfattar ombyggnad av en vägkorsning samt nybyggnad av gång- och cykelbanor. Dessa fyra projekt varierar i omfattning och ger en mer varierad resultat i jämförelse med fyra stycken liknande projekt.

Faktainsamlingen för detta arbete har mestadels omfattat

lean construction med de olika sorters slöseri som finns i byggbranschen samt de olika principerna och metoderna lean construction omfattar, så som Just-In-Time. Andra studier gällande byggprocessen har även gjorts, mer specifikt produktions skedet. Skillnaden mellan värdeskapande och icke värdeskapande tid har behandlats, samt angående riskhanteringen och hur en riskhantering genomförs. Intervjuer har även genomförts i syfte att identifiera de mest kritiska slöserierna och störningar.

Fakta framtagen från intervjuerna har redovisats i resultatet. Där framkom det att de fyra mest kritiska slöserierna var

fel- och omarbeten, väntetider, onödiga transporter och onödiga arbeten. Sammanfattningsvis har åtgärdsförslag med hjälp av lean construction, intervjuer samt kunskap från denna rapport framtagits för att minska på dessa störningar och slöseri med hjälp av t.ex. Jidoka och PDCA för att öka tids- och kostnadseffektiviteten i produktionen.

Kortfattat kan begreppet slöseri och störning definieras på olika sätt. Där slöseri är en aktivitet som inte bidrar med något till verksamheten, och en störning är ett moment som stör arbetet.

Abstract [en]

The biggest challenge construction companies are facing at the moment is reducing the unnecessary costs and labor as well as to streamline the work. This is a matter and an investigation that has been done multiple times in recent years because this is a major problem in most construction companies. This report is commissioned by Peab for the purpose of identifying wastes and critical disorders, then drafting action proposals to reduce waste of time and costs.

Four different, completed construction projects have been investigated, commissioned by Peab, and are located in Stockholm. These projects include the reconstruction of a roadway intersection and new construction of pedestrian and cycle tracks. These four projects vary in scale, giving a more varied result compared to four very similar projects

The gathering of information for this work has mostly included

lean construction with the various waste in the work industry, as well as the different principles and methods of lean construction, such as Just-In-Time. Other studies on the construction process have also been made, more specifically the production phase, the planning of the work. The difference between value creation time and non-value creation time has been dealt with, as well as risk management and how to conduct a risk analysis.

Interviews have also been conducted with the aim of identifying the most critical wastes and interferences.

The gathering of facts from the interviews has been reported in the results.

It emerged that the four most critical wastes were defects/rework, waiting, transportation and extra processing. In summary, action proposals using lean construction, interviews and the knowledge from this report have been developed to reduce these disturbances and wastages with help of for example Jidoka and PDCA to increase time and cost efficiency in the production process.

In short, the concept of waste and disturbance can be defined differently. Waste is an activity that does not contribute anything to the business, and a disturbance is a matter of disturbing the work.

Place, publisher, year, edition, pages
2018. , p. 35
Series
TRITA-ABE-MBT ; 1852
Keywords [en]
Supervisor, site manager, laborer, waste, interference, lean construction, risk management, Just-in-time, Jidoka, PDCA
Keywords [sv]
Arbetsledare (AL), platschef (PC), yrkesarbetare (YA), slöseri, störning, lean construction, riskhantering, Just-in-time, Jidoka, PDCA
National Category
Construction Management
Identifiers
URN: urn:nbn:se:kth:diva-231564OAI: oai:DiVA.org:kth-231564DiVA, id: diva2:1229273
External cooperation
Peab
Educational program
Bachelor of Science in Engineering - Constructional Engineering and Design
Presentation
2018-07-03, 13:19
Supervisors
Examiners
Available from: 2018-07-03 Created: 2018-06-29 Last updated: 2018-07-03Bibliographically approved

Open Access in DiVA

fulltext(1723 kB)12 downloads
File information
File name FULLTEXT01.pdfFile size 1723 kBChecksum SHA-512
38b97dd4275263a0afc91df588605cac3d787ef4097b60f06fc17f9574622ea2cd2ab4245bf7d84e4f034781fa180a2d4f07247d0dace3ea42a32f1ccb9a9c61
Type fulltextMimetype application/pdf

Search in DiVA

By author/editor
Aldebe, WesamTararbit, Yacine
By organisation
Building Technology and Design
Construction Management

Search outside of DiVA

GoogleGoogle Scholar
Total: 12 downloads
The number of downloads is the sum of all downloads of full texts. It may include eg previous versions that are now no longer available

urn-nbn

Altmetric score

urn-nbn
Total: 24 hits
CiteExportLink to record
Permanent link

Direct link
Cite
Citation style
  • apa
  • ieee
  • modern-language-association-8th-edition
  • vancouver
  • Other style
More styles
Language
  • de-DE
  • en-GB
  • en-US
  • fi-FI
  • nn-NO
  • nn-NB
  • sv-SE
  • Other locale
More languages
Output format
  • html
  • text
  • asciidoc
  • rtf