Anläggning av traditionellt VA-schakt: En fallstudie i logistik och byggstyrning
2014 (Swedish)Independent thesis Basic level (professional degree), 10 credits / 15 HE credits
Student thesis
Abstract [en]
A growing issue in the construction industry is how production can become more
efficient by using logistical solutions. Companies can minimize the cost of a project by
reducing the time to perform the work.
The purpose of this report was to examine the logistics related to pipe trenches for
SIAAB. The report's focus has been on solving problems and planning that would
facilitate the work of the project Vaksala-Lunda Etapp 3.
The case study consists of interviews with SIAAB's employees and an observation
where the progress of a traditional pipe trench has been documented using checklists.
Questions to the report’s case study come from the theoretical part, which is based
on literature on construction management and logistics in general. The observation
lasted five weeks and the biggest time-consuming events that affected the pipe trench
during this time, has received most attention. Last part of the report is a compilation
of the authors' own thoughts and opinions.
The production was difficult in this case because the earlier stages of the project were
weak. The extent of SIAAB's planning could have been higher, but this was
complicated when employees were tied to previous projects.
Place, publisher, year, edition, pages
2014.
Keyword [sv]
Logistik, Byggstyrning, VA-schakt, Rörläggning, Planering
National Category
Construction Management
Identifiers
URN: urn:nbn:se:uu:diva-234193ISRN: UTH-INGUTB-EX-B-2014/35-SEOAI: oai:DiVA.org:uu-234193DiVA, id: diva2:755673
External cooperation
Svenska Infra och Anläggningsbyggarna AB
Educational program
Bachelor Programme in Construction Engineering
Supervisors
Examiners
2014-10-202014-10-152014-10-20Bibliographically approved